Chapter 5 / Section 5.11

Dry-docking and grounding

Print this section

The critical instant

When a ship with stern trim enters a dry dock, the stern (the sternframe or the aft end of the keel) touches the blocks first. From that moment, as the water falls, part of the ship's weight is carried by the blocks. The upward reaction PPP at the keel acts below G and behaves like a mass removed from the keel level: it causes a virtual rise of G and a loss of GM. The critical instant is just before the ship touches the blocks along the whole keel ("sewing"), when PPP is greatest and the ship is still afloat enough to heel.

Block reaction at the critical instant

The ship must trim to level keel by the moment the keel takes the blocks along its length. The moment required is P×lP \times lP×l where lll is the distance from the LCF to the point of contact (aft end of keel); it must equal the trimming moment that removes the trim ttt [cm]:

P=MCT1cm×tlP = \frac{MCT1cm \times t}{l}P=lMCT1cm×t​

Loss of GM

Two formulations are in use; both are acceptable, the first is slightly conservative:

GMloss=P KMΔ−PorGMloss=P KGΔGM_{\text{loss}} = \frac{P\,KM}{\Delta - P} \qquad\text{or}\qquad GM_{\text{loss}} = \frac{P\,KG}{\Delta}GMloss​=Δ−PPKM​orGMloss​=ΔPKG​

The effective metacentric height at the critical instant is GMeff=GM−GMlossGM_{\text{eff}} = GM - GM_{\text{loss}}GMeff​=GM−GMloss​ and must remain positive (yards typically require ≥ 0.3 m or a minimum trim limit from the docking plan). KMKMKM should be taken at the reduced displacement Δ−P\Delta - PΔ−P for the first formula.

Grounding

Grounding on a point (rock, bank) is analysed in the same way: the ground reaction PPP at the point of contact replaces the block reaction; its position is generally off-centre and gives a heeling moment P×yP \times yP×y in addition to the GM loss. For a ship aground with falling tide, PPP grows as P=TPC×δTP = TPC \times \delta TP=TPC×δT (fall of water level in cm) when the ship is on a flat bottom, with the appropriate trim correction when aground at one point.

Practical checks in a docking plan

  1. Trim within the limit given in the docking plan (e.g. ≤ 1 m by the stern); no list.
  2. Free surfaces minimised; tanks pressed up or empty as specified.
  3. Effective GM at the critical instant positive with margin.
  4. Block loading and sue (undocking) sequence; keel strength check at the point of first contact.

Formulas

01Block reaction at the critical instant
P=MCT1cm⋅tlP = \frac{MCT1cm \cdot t}{l}P=lMCT1cm⋅t​
SymbolDescriptionUnit
PPPUpthrust from the blocks at the aft end of keelt
tttTrim by the stern on entering the dockcm
lllDistance from the point of contact (aft end of keel) to the LCFm
MCT1cmMCT1cmMCT1cmMoment to change trim 1 cmt·m/cm

Result unit t

02Virtual loss of GM on the blocks (conservative form)
GMloss=P KMΔ−PGM_{\text{loss}} = \frac{P\, KM}{\Delta - P}GMloss​=Δ−PPKM​
SymbolDescriptionUnit
KMKMKMHeight of metacentre at the reduced displacement Δ − Pm

Result unit m

03Virtual loss of GM on the blocks (alternative form)
GMloss=P KGΔGM_{\text{loss}} = \frac{P\, KG}{\Delta}GMloss​=ΔPKG​

Result unit m

Treats P as a mass removed at the keel. Slightly less conservative than the KM form.

04Effective GM at the critical instant
GMeff=GM−GMloss>0GM_{\text{eff}} = GM - GM_{\text{loss}} > 0GMeff​=GM−GMloss​>0

Result unit m

05Ground reaction with falling tide (flat bottom aground)
P=TPC⋅δTP = TPC \cdot \delta TP=TPC⋅δT
SymbolDescriptionUnit
δT\delta TδTFall of water level since touchingcm

Result unit t

Examples

#01

Dry-docking of the example vessel

Worked example

Problem

The vessel enters dock with Δ=6314\Delta = 6314Δ=6314 t, trim 60 cm by the stern, MCT1cm=59.8MCT1cm = 59.8MCT1cm=59.8 t·m/cm, LCF 0.88 m forward of midship, fluid GM=0.70GM = 0.70GM=0.70 m, KM=5.98KM = 5.98KM=5.98 m. The aft end of the keel is at the AP. Find PPP at the critical instant and the effective GM.

Solution

Distance from AP to LCF: l=50.0+0.88=50.88l = 50.0 + 0.88 = 50.88l=50.0+0.88=50.88 m.

P=59.8×6050.88=70.5 tP = \frac{59.8 \times 60}{50.88} = 70.5\ \text{t}P=50.8859.8×60​=70.5 t GMloss=70.5×5.986314−70.5=421.66243.5=0.068 mGM_{\text{loss}} = \frac{70.5 \times 5.98}{6314 - 70.5} = \frac{421.6}{6243.5} = 0.068\ \text{m}GMloss​=6314−70.570.5×5.98​=6243.5421.6​=0.068 m

(alternative form: 70.5×5.28/6314=0.05970.5 \times 5.28/6314 = 0.05970.5×5.28/6314=0.059 m.)

GMeff=0.70−0.068=0.63 m>0✓GM_{\text{eff}} = 0.70 - 0.068 = 0.63\ \text{m} > 0 \quad \checkmarkGMeff​=0.70−0.068=0.63 m>0✓

The vessel can be docked with this trim. Had the trim been 2.0 m, PPP would be 235 t and the loss 0.23 m — still positive, but the yard's docking plan limit on trim and block load would govern.

References

Barrass & Derrett (2012)Clause Ch. 27 (Dry-docking and grounding)Textbook
Rawson & Tupper (2001)Clause Vol. 1, Ch. 5 (Docking and grounding)Textbook
Previous · 5.10Heavy-lift operations and suspended weightsNext · 5.12Damage stability fundamentals: lost buoyancy vs added weight, permeability

Version 2 · last updated 19 Nov 2026 · Editor

On this page

  • The critical instant
  • Block reaction at the critical instant
  • Loss of GM
  • Grounding
  • Practical checks in a docking plan
  • Formulas
  • Examples
  • References

Applicable standards

  • Barrass & Derrett (2012)

    Ch. 27 (Dry-docking and grounding)

  • Rawson & Tupper (2001)

    Vol. 1, Ch. 5 (Docking and grounding)